Wow... a week later its all happening again.

Monday = Roof tiles arrive on site
Tuesday = Sarking, roof battons and all tiling was done - all in a day was an amazing effort
Wednesday = Roof capping done and most of the eave lining installed

Seems like we are flying ahead after this week. Also been told that next week... wait for it..

Tuesday = Electrical
Wednesday = Insulation
Thursday = Gyprocking

Also noticed that the cavity doors were installed in our bedroom and the linen cupboard. There is also a beam that was installed in the rear alfresco to hold the roof up.

Ivan is back from Perth and doing a floor across the road from our house. I have to squeeze him in to get the job done before the gyprock goes up next week. Now the roof is done I also have to go to site on Saturday to take the floor protection up and clean the inside of the house ready for the floors to be polished - Dirty Job but someone has to do it!

Seriously cant wait to see these floors finished.

Better photos to come this weekend... PROMISE